Procurement Management and Purchase Order Execution on the Critical Path - A Key Success Factor in Construction and Infrastructure Projects

  • Daniel Asseraf, DVIEWSION CEO
  • 2 days ago
  • 3 min read

In our project management activities at DVIEWSION, we regularly work with real estate developers who challenge project schedules in an effort to maximize profitability. High-rise construction and infrastructure projects—particularly in new buildings with advanced systems—are characterized by a high number of interfaces, tight timelines, and strong interdependencies between tasks and suppliers.These conditions require us to treat procurement management and the issuance of purchase orders as decisive factors that directly impact the overall project schedule, budget, and quality. When these activities fall on the critical path, their importance becomes dramatic.


What Is the Critical Path?

The critical path is the longest sequence of interdependent tasks from the start of the project to its completion. A delay of even one day in any task on this path will immediately result in a one-day delay to the overall project completion.


The Role of Procurement and Purchase Orders on the Critical Path

When a procurement activity or purchase order is located on the critical path, it means that:

Availability of materials and services dictates construction progress:If a critical task depends on specialized equipment—such as a custom transformer, tailor-made steel beams, or a large industrial pump—any delay in ordering, manufacturing, or delivery will delay the start or completion of that task.

Implications for planning and execution:Purchase orders are often dependent on the completion of detailed design, while the execution of subsequent phases depends on timely delivery of procured items. Gaps or bottlenecks in this process disrupt the entire supply chain and construction workflow.

The Importance of Proactive Procurement Management

To prevent such critical delays, a proactive approach to procurement management is required:

Early identification of critical procurement items:At the outset of the project, all components, suppliers, and subcontractors with long lead times for supply or installation must be mapped and managed as critical items.

Long-lead procurement:Items with exceptionally long delivery times—particularly those sourced from Europe or Asia, which may take several months—must be approved and ordered at very early planning stages, sometimes even before detailed design of other systems is finalized.

Acceleration of approval processes:Dedicated resources should be allocated to shorten tendering, technical evaluation, negotiation, and contractual approval processes for critical orders. A one-week delay at a procurement committee level can easily translate into a one-month delay in actual delivery.

Aggressive supplier management:Continuous and precise monitoring of manufacturing and delivery progress is required, including site visits to production facilities when necessary, as well as strict enforcement of schedules and contractual commitments.

Key Strategies

Integration between design and procurement:Design, procurement, and project management teams must operate in full synergy. Design must account for market lead times, while procurement must receive specifications at the exact time required.

Buffering critical activities:Despite aggressive management, unforeseen risks always exist (strikes, port delays, last-minute design changes). Limited schedule buffers may be added to delivery times for critical items, but these buffers must be carefully managed to avoid deviation from overall project targets.

Cost–benefit analysis:When critical procurement is at risk, it may be justified to pay a premium—such as for expedited shipping or overtime at manufacturing plants—to avoid penalties and indirect losses caused by delays to the entire project.


Conclusion

Managing procurement and purchase orders on the critical path lies at the very heart of successful construction and infrastructure project delivery. Through early planning, proper prioritization, process acceleration, and tight integration between all stakeholders, it is possible to ensure a continuous flow of resources, prevent costly delays, and deliver projects on time, within budget, and at the required level of quality.


 
 
 